Peshawar rapid bus service finally gets a go-ahead

mhafeez

Chief Minister (5k+ posts)
Peshawar rapid bus service finally gets a go-ahead

PESHAWAR: The Provincial Development Working Party on Tuesday approved the execution of the much-anticipated Peshawar Sustainable Bus Rapid Transit Corridor Project, whose cost increased by around Rs20 billion over a period of time.

U.S.-Bus-Rapid-Transit-Report-Cover.jpg


The project secure approval during a meeting held here. The Rs57.23 billion project will be completed with the help of the Asian Development Bank.

Of the total cost, the provincial government will secure Rs50 billion from the ADB and contribute around Rs7.23 billion from own resources.A project presentation shared with Dawn showed that the project would be sent to the Central Development Working Party (CDWP) for approval.

According to it, the project will be completed within 12 months with the aim to introduce a well-designed, comfortable and user-friendly public transport and provide commuters with a reliable, safe, affordable and high quality bus rapid transit service in the provincial capital.

The corridor will be around 261(ilometers long with 15 1(ilometers street level stretch, six kilometers long elevated portion and five kilometers tunnels.

The BRT will have 32 stations, two depots, 68 kilometers feeder bus routes, 150 bus stops, 450 buses, six storied parking plaza and 61 acres of commercial plaza.

Its infrastructure and depots will cost Rs39.27 billion, utility relocation Rs4.2 billion, fleet scrapping and environmental mitigation Rs1.11 billion and fleet procurementRs7.78 billion.

The presentation said the project`s cost had gone up by almost Rs20 billion due to the20percentincreaseinthecostoftheproject on market rate system to accommodate international bidding, inclusion of Sunehri Masjid alignment, inclusion of institutional costs, resettlement costs, land acquisition, resettlement plan, utilities relocation, nancingcharges and neetscrapping.

`The department will forward a summary to the chief minister on the 20 percent cost escalation over the MRS,` it added.

According to the documents, the BRT corridor will begin from Chamkani and would go along the GT Road `at-grade` until Gulbahar, where it will elevate to the bypass junction.

Once it passes the junction, it will be `atgrade` again until Firdous Cinema and will turn left near Bala Hisar Fort through a tunnel to the Khyber Bazaar and go on to Soekarno Square, Railway Road andDabgari, where it is elevated all the way through Sunehri Masjid Road. From there, it will go `at-grade` past the Mall, Khadim Hussain Road and Sir Syed junction up to Aman Chowk.

The BRT corridor will pass through the Aman Chowk by a tunnel. It will be at the street level up to Hayatabad, It will turn left near Bab-i-Peshawar bridge and elevate through dried river bed to old sewerage treatment plants before going at street level Habib Jalib Road toward Bagh-e-Naran.

There will be its only flyover crossing dry riverbed opposite the Bagh-i-Naran. From there, the corridor will turn right towards Tatara Park and Peshawar Development Authority building before ending on Jamrud Road with its last stop at the Cancer Hospital.

BRT project director Sajjad Khan wasn`t available to respond to questions on the project despite repeated contacts by Dawn on his cellphone number.

Dawn
 
Last edited by a moderator:

Will_Bite

Prime Minister (20k+ posts)
The amount of red tape in our country is just atrocious. I guess that is one reason why people dont mind military rule.
 

lurker

Chief Minister (5k+ posts)
Halal or Haram; I think the People of Pakistan deserve Rapid Transport. Not just buses but also Metro Rail. After 70 years of Pakistan, we Pakistanis don't care about Halal or Haram; Just get it done. We will sort out the Halal Haram in the after life.
 

mhafeez

Chief Minister (5k+ posts)
The amount of red tape in our country is just atrocious. I guess that is one reason why people dont mind military rule.


Yes, the bureaucracy wasted millions for three time feasibility studies, many designs and re-designs. But after every study the cost increases manifold.
 
Last edited:

mhafeez

Chief Minister (5k+ posts)

اسکا روٹ وسیع کر دیا گیا ہے

اس کا روٹ کتنے کلومیٹر تھا اسکا کتنے کلومیٹر ہے ؟؟ ویسے جس میٹرو کا اسد عمر نے کہا تھا اسکا روٹ ٢٢.٥ کلومیٹر ہے
 

Nice2MU

President (40k+ posts)
وہ چار ارب والی میٹرو کا کیا ہوا؟؟


Initial plane was not BRT but a simple lane along with Railway Track but I don't know whether Nooras gona sell that land or what that they didn't allow it. So KP govt brought completly new idea of BRT which is not a single lane metro but along with 26 Km main artery there would be more than 6 smaller routs as well with about 84 km roads, over 100 bus stops and over 350 buses.

Lahore, Pindi and Multan Metros didn't change the face of the cities but BRT will completly change the face of Peshawar because it very extensive and it would carry more than 4.5 Lakh people on daily bases where Lahore Metro carries about 1 to 1.5 Lakh people daily.

BRT Peshawar would cover around 40-45 % (this is my guess) or even more part of Peshawar. So don't take it like the existing Metros in the country.
 
Last edited:

akmal1

Chief Minister (5k+ posts)
اس کا روٹ کتنے کلومیٹر تھا اسکا کتنے کلومیٹر ہے ؟؟ ویسے جس میٹرو کا اسد عمر نے کہا تھا اسکا روٹ ٢٢.٥ کلومیٹر ہے

لاہور والا کتنے کلومیٹر کا ہے؟ کتنے میں بنا؟ اسکا ریکارڈ کہاں ہے؟ جو بن چکا ہے پہلے اسکا حساب لے لو
 

mhafeez

Chief Minister (5k+ posts)

لاہور والا کتنے کلومیٹر کا ہے؟ کتنے میں بنا؟ اسکا ریکارڈ کہاں ہے؟ جو بن چکا ہے پہلے اسکا حساب لے لو

لاہور میٹرو مین روٹ ستائیس کلومیٹر ہے کل لاگت ٢٩.٨ ارب روپے تھی اس سال اس میں پانچ کلومیٹر کا مزید اضافہ ہو جائے گا جس پر دو ارب روپے خرچہ آئے گا جس سے اسکی لاگت بتیس ارب ہو جائے گی اگر میٹرو فیڈر بس روٹ کو بھی شامل کریں تو ١٢٩ کلومیٹر کے لئے مزید تین ارب خرچ ہوۓ

اب آپ کی بری ہے حسب دینے کی
 

akmal1

Chief Minister (5k+ posts)
لاہور میٹرو مین روٹ ستائیس کلومیٹر ہے کل لاگت ٢٩.٨ ارب روپے تھی اس سال اس میں پانچ کلومیٹر کا مزید اضافہ ہو جائے گا جس پر دو ارب روپے خرچہ آئے گا جس سے اسکی لاگت بتیس ارب ہو جائے گی اگر میٹرو فیڈر بس روٹ کو بھی شامل کریں تو ١٢٩ کلومیٹر کے لئے مزید تین ارب خرچ ہوۓ

اب آپ کی بری ہے حسب دینے کی

جب بن جائیگی تب حساب دے دیں گے. چلو شاباش. مستقبل کا حساب لینے والا پہلا انسان دیکھا ہے
 

akmal1

Chief Minister (5k+ posts)
Halal or Haram; I think the People of Pakistan deserve Rapid Transport. Not just buses but also Metro Rail. After 70 years of Pakistan, we Pakistanis don't care about Halal or Haram; Just get it done. We will sort out the Halal Haram in the after life.

یہ کمائی والا حلال حرام نہیں ہے. عوام کا پیسا کھانے والے حکمران کے ذریعے ترقی کا قانون خدا نے رکھا ہی نہیں ہے. یہ کونسی منطق ہے کہ ٧٠ سال گزر جائیں تو حلال حرام سب ایک ہو جاتا ہے؟ یہ کہاں پڑھا ہے؟ سادہ عقل کی بات ہے کہ جب ایک جگہ ضرورت سے زیادہ پیسا لگایا جائیگا تو بہت سی اور جگہیں ضرورت سے محروم رہ جائینگی اور یہ سب نظر بھی آ رہا ہے. لاہور اور باقی پنجاب کا فرق دیکھ لو. حلال حرام اسی دنیا میں کرنا ہوتا ہے اگلی دنیا میں خدا کرے گا تم نہیں
 

Will_Bite

Prime Minister (20k+ posts)
لاہور میٹرو مین روٹ ستائیس کلومیٹر ہے کل لاگت ٢٩.٨ ارب روپے تھی اس سال اس میں پانچ کلومیٹر کا مزید اضافہ ہو جائے گا جس پر دو ارب روپے خرچہ آئے گا جس سے اسکی لاگت بتیس ارب ہو جائے گی اگر میٹرو فیڈر بس روٹ کو بھی شامل کریں تو ١٢٩ کلومیٹر کے لئے مزید تین ارب خرچ ہوۓ

اب آپ کی بری ہے حسب دینے کی
That is the most amusing maths I have seen. Is this the same computation that was lost in the LDA fire?

And any kind words for the annual payout to the turkish contractor?
 