Peshawar metro bus cost swells to Rs68b
The cost of Peshawar Metro, Peshawar Sustainable Bus Rapid Transit Corridor Project (BRT), has increased by 38 percent from Rs49.3 billion to Rs67.9 billion and the Planning Ministry has said that proper working on the design of the project was not carried out at the preliminary design stage which has resulted in such a huge increase.
From preliminary design phase to detailed design phase, there are generally no major deviations as is in this case which have resulted in 38 percent increase in cost from the original, said the Transport &Communication Section of the Planning Ministry said in its comment on the revised PC-I of the Peshawar Sustainable Bus Rapid Transit Corridor Project (BRT).
Despite decrease in the number of buses and reducing the stations the cost of one kilometer, of ill planned BRT, has increased from Rs1.8 billion to Rs2.3 billion, said the revised PC-I of the project.
The revised PC-I will be discussed by the CDWP Monday (today). The government of PTI in the province has ended but the people of KP is still paying high price for the defective planning and lose management in the execution of BRT.
Peshawar Sustainable Bus Rapid Transit Corridor Project (BRT) was started in December 2017 by the then PTI government with an estimated cost of Rs49.3 billion and its entire work will be completed by February 2019.
The Nation
The cost of Peshawar Metro, Peshawar Sustainable Bus Rapid Transit Corridor Project (BRT), has increased by 38 percent from Rs49.3 billion to Rs67.9 billion and the Planning Ministry has said that proper working on the design of the project was not carried out at the preliminary design stage which has resulted in such a huge increase.
From preliminary design phase to detailed design phase, there are generally no major deviations as is in this case which have resulted in 38 percent increase in cost from the original, said the Transport &Communication Section of the Planning Ministry said in its comment on the revised PC-I of the Peshawar Sustainable Bus Rapid Transit Corridor Project (BRT).
Despite decrease in the number of buses and reducing the stations the cost of one kilometer, of ill planned BRT, has increased from Rs1.8 billion to Rs2.3 billion, said the revised PC-I of the project.
The revised PC-I will be discussed by the CDWP Monday (today). The government of PTI in the province has ended but the people of KP is still paying high price for the defective planning and lose management in the execution of BRT.
Peshawar Sustainable Bus Rapid Transit Corridor Project (BRT) was started in December 2017 by the then PTI government with an estimated cost of Rs49.3 billion and its entire work will be completed by February 2019.
The Nation